Strong Road - Five Mile to Cannon - 2022095

This project consists of the construction of approximately 2,400 cubic yards of excavation and embankment, 7,900 square yards of cement treated base, 7,900 square yards of 5-inch thick HMA pavement, 1,300 square yards of 3-inch thick HMA pavement, sundry utility adjustments, and other related miscellaneous items.

Status

Bidding Closed

Bid Date 6/12/23 1:00pm

Company & Contacts

City of Spokane Engineering Dept.
Rich Proszek  
(509) 625-6700

Location

Spokane, WA

This site is for the “General Public”. If you are a Bidder, Sub-bidder or a Supplier, go back to City of Spokane Plan Room and choose the “Bidders Access” option

If you add yourself to the plan holders list you WILL NOT be notified of changes to this project.